Project Showcase

We innovate and deliver technical expertise to find the right solutions!

AG Barr Effluent System

Joseph Gallagher were appointed to carry out works for creating a new effluent system named “Project Ginger” for AG Barr the makers of the famous Irn Bru.

  • CLIENTAG Barr

  • CONTRACTORAG Barr

  • LOCATIONScotland

  • EXPERTISECivil Engineering, Design

  • SERVICESFoundations/Groundbearing Slabs | Groundworks | Open Cut | Paving and External Works | Reinforced Concrete | Sheet Piling

An Overview

Works included

  • Excavation and construction of a RC tank foundation/ bunded area. The RC foundation had two plinths for future storage tanks
  • Excavation and installation of an underground GRP Tank and associated pipework.
  • Casting of concrete turrets and installation of Technocovers
  • Excavation, installation and electrofusion welding 140m of 100mm HDPE pipe.
  • Excavation and installation of 355mm Polypropylene pipe and construction of manhole for outlet connection to existing line,
  • Construction of Kiosk Base and install of ducting

Services and works undertaken:

  • Foundations/Groundbearing Slabs
  • Groundworks
  • Open Cut
  • Paving and External Works
  • Reinforced Concrete
  • Sheet Piling

Our Design Team provided the temporary works designs for the sheeted pit for the Spel Tank and the Trench Box for 355mm polypropylene pipe.
We logged over 600 incident free hours on the project and successfully completed the works ahead of the commissioning date required by the client.

Download AG Barr Case Study

Would you like us to send you this case study?

By submitting your name and email address you are opting in to receive emails.
For more information on this, read our privacy policy