- Sector:
- Water and Wastewater
- Client:
- Southern Water
- Main Contractor:
- Galliford Try
- Location:
- Budds Farm
Contact usTo hear about our experiences and how we can help you.
Challenges
The project presented several technical and logistical challenges, including:
- Very restricted working areas within a live treatment works
- Multiple contractors operating concurrently in close proximity
- High groundwater levels, influenced by a tidal river
- Poor site security, increasing exposure to theft
- High staff turnover, requiring careful management to maintain continuity
These challenges were successfully mitigated through strong site leadership, clear communication, and collaborative working practices.
Added Value
Joseph Gallagher Ltd provided additional value by supporting the redesign of the storm overflow system, improving its hydraulic efficiency and overall performance. This collaborative input enhanced the functionality of the final scheme while supporting Southern Water’s long‑term operational objectives.