Doggerbank Onshore Wind Farm

One of the Group's flagship projects - showcasing our HDD capabilities. Jones Bros commissioned JGL to support closely on the installation of the HVDC cable ducting system.

Sector:
Digital Infrastructure
Client:
Dogger Bank Wind Farm
Main Contractor:
Jones Bros Civil Engineering
Location:
East Ridings of Yorkshire
  • Operating four horizontal directional drilling rigs simultaneously during peak times,
  • Installing an impressive 27km of duct in 140 drills – ranging from 50m to 620m,
  • Great example of collaboration and exemplary team work ethic from the JGL team.

Contact usTo hear about our experiences and how we can help you.

Project Overview

One of the Group's flagship projects showcasing our HDD capabilities. JGL were commissioned to help support Jones Bros with the installation of the HVDC cable ducting system by undertaking a series of Horizontal Directional Drills in preparation for the install.

This forms the integral cable work onshore to drive future transmission of renewable energy from the world's largest offshore wind farm to UK homes and businesses.

Challenges

The soft ground conditions - including sand, clay, gravel, and peat - presented a significant challenge for the team. To accommodate these conditions, we procured a bespoke Dupagro de-sander system suitable for the anticipated soils. Additionally, we adjusted the tooling and switched the HDD drilling slurry to a CEBO OCMA‑approved product.

The project required exceptional planning and logistics, as the crossings were designed to pass beneath roads, railways, rivers, and multiple Sites of Special Scientific Interest (SSSI).

Working closely with our design team, we developed bespoke designs for each crossing, mitigating the associated risks and incorporating environmentally friendly materials throughout the works.

JGL at Doggerbank Wind Farm

Added Value

A real benefit to the client has been the exceptional collaboration from the offset. Supporting from the tendering stage of the project really added value and reassurance for delivering the project at the highest of standards.

Utilising our Group services and assets enhanced productivity and operational safety benefits to the project.

Our design team based in Leeds were involved early with both temporary and permanent design works with our Group subsidiary NRC Plant, providing excavators.

Our award-winning LIFE safety culture was been embedded on the project from day one, along with our Prevention Not Correction initiative. To date no safety or non-conformance issues were reported.

Aerial view of the onshore construction area

This has been a fantastic project to work on over the past two years. Our team have been instrumental throughout, operating four horizontal directional drilling rigs simultaneously during peak times, installing an impressive 27km of duct in 140 drills – ranging from 50m to 620m and then returning to grout the cables after the install. It’s been a true collaborative effort working with Jones Bros throughout the project. The team’s work ethic shone through helping to deliver the project to programme and with safety at the forefront - something we are very proud to have been part of.

Tony Matheson

Group Commercial Director, JGL

To hear about our experiences and how we can help you.

Explore related content

Civil and Structural Works

250620 JGL Finham 604

Services

Specialists in civil and structural works, delivering safe, precise construction, reinforced concrete, steel structures, and infrastructure solutions.

Ground Improvement and Enabling Works

Services

Specialists in ground improvement and enabling works, delivering safe site preparation, remediation, utilities, drainage and construction readiness.