Project Overview
Joseph Gallagher Ltd (JGL) successfully delivered the TRS08A Auger Bore Crossing as part of the wider Liverpool Bay Carbon Capture Storage Project.
The works comprised the installation of a 36-metre auger bore drive using a BM800-L2S auger boring machine, installing a 36-inch (914 mm OD) steel product pipe with a wall thickness of 22.23 mm.
The project was completed on programme and within budget with an average workforce of five operatives on site and delivered with no non-conformities in full coordination with United Infrastructure.
Scope of Works
JGL was responsible for execution of the auger boring works, including:
- Installation of a 36 m auger bore crossing
- Jacking of three steel pipe sections (2 × 9 m, 1 × 18 m)
- Operation of the BM800-L2S auger boring machine
- Pipe installation through sand and clay ground conditions
- Management of excavated material and controlled jacking pressures
Shaft construction, welding, and coating were undertaken by United Infrastructure.