Sector:
Water and Wastewater
Client:
Essex and Suffolk Water
Main Contractor:
Galliford Try
Location:
Gallows Corner - Romford

Contact usTo hear about our experiences and how we can help you.

Project Planning Overview

Joseph Gallagher Group’s extensive experience in shaft and tunnel construction has been fully leveraged to develop a robust and practical plan for the Gallows Corner MT works. Drawing on lessons learned from previous projects, the team has ensured seamless integration of design, site, and micro‑tunnelling considerations. The micro‑tunnelling team has maintained continuous communication with both design and site teams, proactively identifying challenges and optimising construction sequences. Comprehensive risk assessments, resource planning, and programme coordination have been applied to drive efficiency, enhance safety, and minimise disruption throughout delivery. This collaborative and experience‑driven approach demonstrates JGL’s commitment to providing high‑quality, reliable, and timely tunnelling solutions.

Project Highlights

The tunnel and product pipeline installation were completed without any incidents, demonstrating strong planning, coordination, and adherence to safety standards throughout the works. Despite delays beyond JGL’s control, the project was successfully delivered on schedule, meeting all scheduled targets and maintaining a high level of quality from start to finish. In addition, the full quality handover package was prepared, verified, signed off, and formally submitted to the client ahead of the contractual completion date, ensuring a smooth and efficient close‑out process.

Project Challenges

Initially, the shaft was designed with a 7 m diameter; however, the presence of multiple live cables running through the shaft collar required the diameter to be reduced to 5.5 m. This design change also meant that the product pipe sections installed within the tunnel had to be shortened, with 4 m lengths used instead of the original 5.5 m lengths to suit the revised shaft geometry and ensure safe handling during installation. Another significant challenge arose where the TBM was required to pass beneath an uncharted manhole (MH), for which the depth had not been confirmed.

A detailed design assessment was undertaken to evaluate ground conditions, loading effects, and potential movement to ensure that no structural damage would occur to the manhole as the TBM advanced underneath. This assessment was essential in verifying the safety of the alignment and ensuring the tunnelling operation could proceed without risk to existing assets.

JGL Gallows Corner MT

Commitment to On‑Time Delivery

Tunnel works were delivered by operating both day and night, ensuring continuous progress throughout the programme. Where required, weekend working was also utilised to maintain momentum and avoid delays, providing the flexibility needed to keep the operation moving at critical stages. This commitment to extended working hours ensured that productivity remained high and enabled the project to be completed on time, demonstrating a proactive approach to meeting programme demands and delivering added value for the client.

Innovations

1. Use of Jacking Rig for Pipe Installation
Using a jacking rig to install the product pipe inside the tunnel, instead of a conventional mechanical pulling method, provided several technical and commercial advantages.

The decision to use a jacking rig offered the following benefits:

  • Controlled Installation – Hydraulic jacking allows precise, gradual pipe advancement, reducing the risk of pipe damage.
  • Reduced Stress on Pipe – Unlike pulling methods that place tensile stress on the pipe, jacking applies compressive force, which is often more suitable for product pipe installation in confined tunnels.
  • Improved Safety – Eliminates long pulling setups and associated hazards. Better Alignment Control – Particularly beneficial in tunnel environments where accuracy is critical. Reduced Plant Requirements – Avoided the need for additional winches, long pulling frames, or heavy pulling equipment.

Overall, this approach improved installation efficiency while reducing risk and potential damage.

2. Use of Surplus Type 1 Material for Crane Pad Construction
Utilised surplus Type 1 material (meeting required specification) sourced from another contractor on site for construction of the crane pad, instead of procuring new material.

Technical Overview

Reception pit (Size / Construction) - 10x3m ID sheet piled reception pit
Tunnel size (Dia / length) - 1200 ID Mirco TBM drive 55m length
Tunnel lining - Jacking Pipes
TBM Machine Model, Size & No. etc. - Iseki 1400, OD 1450- 1 no.
Completed Drive Length (m) - 55 m
Diameter of tunnel / pipe (mm) - 1200mm
No. of crossings - 1
Ground Conditions - London clay
Concrete Poured m3 - 70.5
Muck Away m3 - 1250
Installation of product pipe - 60m of 945mm OD ductile iron pipe works with electro lock joints
Testing of product pipe - Hydrostatic test of product pipe

Services Provided

Design – Temporary Works
Design of temporary works for crane pads at the drive shaft
Temporary works design for the reception pit
Design and installation of Davit Arms for lifting and access operations

Design – Permanent Works
Permanent works design for the shaft
Design of the reception pit
Permanent design for the tunnel alignment and associated structures

Micro‑Tunnelling Works
Installation of 1200 mm ID jacking pipes over a 55‑metre drive
Execution of micro‑tunnelling operations to facilitate placement of the carrier/main pipe

To hear about our experiences and how we can help you.

Explore related content

Tunnelling and Underground Works

Operative walking through tunnel

Services

Specialists in tunnelling and underground engineering, delivering safe, precise excavation, ground support, and subsurface infrastructure solutions.

Civil and Structural Works

250620 JGL Finham 604

Services

Specialists in civil and structural works, delivering safe, precise construction, reinforced concrete, steel structures, and infrastructure solutions.

Specialist Plant and Equipment

Specialist Plant and Equipment

Services

SPA and NRC are experts in lifting and plant solutions, providing safe, precise deployment, operation and maintenance of advanced machinery.

Ground Improvement and Enabling Works

Services

Specialists in ground improvement and enabling works, delivering safe site preparation, remediation, utilities, drainage and construction readiness.