- Sector:
- Energy - Marine
- Client:
- Jones Brothers
- Location:
- Holy Island, Anglesey, North Wales
Contact usTo hear about our experiences and how we can help you.
Project Delivery
Drawing on the information gathered during the investigation phase, the team proposed an HDD installation at a depth of approximately 12 metres beneath the busy transport corridor. This approach significantly reduced disruption to the travelling public while protecting critical local infrastructure.
The final solution utilised American Augers DD1005 drilling equipment, combined with advanced rock-cutting technology to successfully navigate the challenging geological conditions. A Vermeer 60/90 drilling rig was also deployed to complete the HDD installation, supported by a full design service that included engineering calculations and geotechnical appraisal.
The works were completed safely, on programme and within budget. Through careful planning and the adoption of trenchless construction methods, the project was delivered without disruption to road users, rail operations or other essential infrastructure, enabling the successful installation of the electrical connection required for the Morlais Tidal Energy Scheme.

To hear about our experiences and how we can help you.