Project Title

A9 Lynbeg Bridge

Summary

Our scope involved the installation of a new UTX pipeline to allow a temporary diversion of utilities prior to the construction of the new bridge.

Services

Value:
£542,000
Sector:
Infrastructure
Client:
Network Rail
Main Contractor:
BAM Nuttall
Location:
Scotland
Duration:
10 weeks
  • Fulfilling National Rail's strict deadline was a huge achievement as the rail connection is an essential route,
  • JGL's Design Team successfully re-configured the Network Rail forms efficiently to enable works to commence on time
  • No accidents were reported on site given the narrow parameters of working within a public area.

Contact usTo hear about our experiences and how we can help you.

Project Overview

Joseph Gallagher was appointed by main contractor, BAM Nuttall to deliver a package of works that required the installation of a new UTX (Under Track Utility Crossing) pipeline to allow a temporary diversion of utilities prior to the construction of the new bridge. The works were part of the A9 improvements - the main rail connection in and out of North Scotland.

Our in-house design services were used for the UTX crossing design and application process.

Critical changes to the proposed size of pipeline were required, to adapt to challenging ground conditions, which became apparent after mobilisation.

Challenges

The fundamental challenge on this project was the existing ground conditions. We had supplied design and delivery solutions based on the usage of a standard TBM. However, after mobilising on site and constructing the drive and reception pit/shaft, we were exposed to very hard boulders in the shaft and tunnel horizon, raising concerns on the TBM suitability to the existing ground to be tunnelled through. As a result we overcame this with our sister company being able to rapidly send a TCS 1200 to the site from their base in Northampton, within 2 days. We instructed our in-house design team to step in and urgently re-design a solution without compromising the programme.

The excavation shaft was between the railway and local road caused challenges of its own, however most of the major works we consciously scheduled to take part during less busier times of the day. Traffic Management and Pedestrian Management Plans were drawn up with BAM and implemented successfully to ensure the public safety and access were prioritised.

The location of the site itself was remote from our subsidiary firms so it was integral for the PM to build in delivery and logistical time factors into the programme to minimise impact to a critical programme set by National Rail.

Shaft at A9 Lynbeg Bridge
Shaft at A9 Lynbeg Bridge
Drive complete
Drive complete at A9 Lynbeg Bridge

Added Value

Our nationwide capability offered BAM a single source procurement route for the design and build of the UTX, taking ownership and minimising any risk between the design and construction phases. Adding to this was our internal design team working closely with our operational delivery team to undertake the Network Rail asset standard F001, 002, 003 detailed design and obtain approval on time to commence the works.

Internal access of our Group subsidiary Iseki Microtunnelling allowed tunnelling plant allowed quick replacement of the TBM and tunnelling equipment when unforeseen ground conditions were encountered.

To hear about our experiences and how we can help you.

Explore related content

Enabling Works

Services

Not only do we deliver on major projects - we frequently are called upon to deliver Enabling Works on projects of all scales to ensure that sites are ready for major works to commence.

Temporary Works

Services

Temporary Works are an essential part of any project. Boasting a multi-skilled workforce and inhouse design team - we collaborate, design and deliver bespoke solutions for our clients.

Shield Driven Tunnels

Services

Tunnelling is a service that requires a wealth of experience, due to its wide range of sizes, shapes and environments. Our Shield Driven Tunnelling solution starts from 1.2m diameter tunnels to 7.15m.