Acton Storm Tanks (Syphon Main Diversion)

Balfour Beatty, Morgan Sindall and BAM Nuttall (BMB JV) approached JGL to tender for the works for the installation of a new 900mm id concrete pipeline and connections into two manhole chambers.

Sector:
Utilities
Client:
Thames Tideway
Main Contractor:
Morgan Sindall & BAM Nuttall JV
Location:
London

Contact usTo hear about our experiences and how we can help you.

Project Overview

Joseph Gallagher are proud to have already completed several major projects for Thames Tideway across all three sections of the project since 2018.

Balfour Beatty, Morgan Sindall and BAM Nuttall (BMB JV)the delivery partner approached JGL to tender for the works, which involved the installation of a new 900mm diameter concrete pipeline and connections into two existing manhole chambers.

Following our appointment, the final scope of works consisted of installing two sheeted pits at 6m deep and microtunnelling a distance of 45m with final connections into the existing two manhole chambers.

Challenges

The single biggest challenge facing the project was the risk of settlement during the works. The correct method of works and sequencing was instrumental for keeping any potential settlement to a minimum. We proposed installing a line of driven sheet piles on the boundary side adjacent to the highway, where key utility services were located. Careful consideration was also given to the type of piling implemented, a pre-augering with a pile press solution was adopted as it allowed the settlement to be kept to a minimum.

There were multiple obstructions that needed to be removed as the shaft excavations proceeded downwards. This resulted in a 'dig a push' method for the remaining side of the shaft. JGL were able to lean on the Group's extensive services and resources to complete these complex works.

Added Value

  • Repeat work on Tideway projects meant that we were able to offer a trained, inducted and highly experienced team with ease.
  • Design innovation offered through our design service to simplify connections to the existing sewer and ground settlement risk during the pit excavation.
  • An extensive and highly trained tunnelling workforce plus rapid access to Group subsidiary assets such as microtunnelling equipment and crane hire from NRC Plant Ltd and SPA, allowed valuable project efficiencies to benefit both the project and client.
Microtunnelling underway at Acton

To hear about our experiences and how we can help you.

Explore related content

Civil and Structural Works

250620 JGL Finham 604

Services

Specialists in civil and structural works, delivering safe, precise construction, reinforced concrete, steel structures, and infrastructure solutions.

Design and Engineering

Services

Experts in specialist plant and equipment providing safe deployment, operation, and maintenance of advanced machinery for complex infrastructure works

Specialist Plant and Equipment

Specialist Plant and Equipment

Services

SPA and NRC are experts in lifting and plant solutions, providing safe, precise deployment, operation and maintenance of advanced machinery.

Environmental and Sustainability Services

Services

Delivering low impact, eco-conscious solutions that protect the environment in infrastructure, enhancing sustainability and regulatory compliance.