Project Overview
JGL were commissioned by main contractor FLO to deliver a CSO (combined sewer outfall shaft) alongside an SCL connection tunnel into the Tideway main drive.
Without the skills and commitment from our brilliant team along with the SCL mix design – we simply would not have been able to consistently pump from a single point onto the surface.
Challenges
The most significant challenge on this project was in the 250m-long connection tunnel. The diameter and length of the drive meant that we had to be very selective with the choice of plant used to complete the drive. Initially, the Wimmer Blue Badger was used to excavate the first half of the tunnel and then we reverted to the SPA Schaeff 112 for the second stage.
The second challenge of getting concrete to the spraying robot was significant considering the distance the material had to travel from the silos on the surface (300m). Initially, concrete remixers were considered however, the diameter of the tunnel eliminated this option as the remixers simply would not fit.
That left the option of pumping from the surface which introduced the risk that the Meyco Suprema pumps might not have capacity to pump the concrete the required distance. To overcome this, we had the backup plan of stage pumping with additional pumps and the fabrication additive storage gantry.